The customer wanted to modernise the entrance hall and renovate the toilet. After removing the doors and old doorframes I started the demolition of the toilet. I installed 3 new hardwood doorframes in 3 different sizes with new doors (1 small door had to be custom made). When the doorframes were installed I finished the top with plasterboard and had it all plastered. Installed new door trim, skirting all around (both timber and stone) and had it all painted. The toilet was fairly straightforward by replacing the existing toilet frame with a new one, built a new lowered ceiling with timber and plasterboard and tiled everything with tiles chosen by the customer.
I did most of the work myself, only the plastering and tiling were done by a third party.